To investigate a sales-to-implementation handoff, compare what Sales promised with what Implementation received, then record missing context, acceptance time, and the reason for each delay. This fictional worked example shows how to check competing explanations before testing a change.
The case and its limits
This is a fictional 25-person service business, not a customer case study. Of five kickoff attempts, three needed another request for scope details. Sales used a CRM, implementation used a project board, and nobody recorded when implementation accepted the handoff. Those supplied facts establish a symptom, not its cause.
What to inspect
For each case, compare the signed scope, commitments recorded during the sale, the brief sent to implementation, clarification requests, and actual acceptance time. Ask both roles to review discrepancies. A delayed kickoff might also reflect delivery capacity, client availability, or a dependency outside either team's control.
Hypotheses and evidence that could distinguish them| Hypothesis | Supporting observation | Countercheck |
|---|
| Scope details are missing | The same omission recurs in returned briefs | Do complete briefs also wait? |
| Delivery lacks capacity | Ready work queues despite acceptance | Were delivery slots available for delayed cases? |
| Customer dependencies block work | Required access arrives late | Was that dependency agreed before the promise? |
A bounded intervention
If missing scope is the recurring blocker, test the readiness and acceptance checklist on the next five comparable transfers: promised deliverable, deadline, exclusions, unresolved questions, and receiving owner. Implementation records acceptance or a specific exception. If feasibility remains uncertain before signing, arrange a review for those cases rather than requiring an extra meeting for every sale. The professional services delivery handoff guide explains feasibility ownership and the internal kickoff.
The seven-day review
Use sending-to-acceptance time, clarification count, and time spent completing the brief. Keep measurement definitions consistent with the baseline. Record unusual projects and customer delays separately. Stop or simplify the check if it adds effort without resolving the missing context. If complete briefs still queue, test the capacity explanation next.
What this example does not prove
It does not establish a universal sales incentive problem, quantify lost revenue, or promise savings. Small samples and self-reported accounts cannot establish causality. Review the findings with the people involved before changing responsibilities or commitments.